Georgia-Pacific commits about $150 million to Palatka paper-machine rebuild
Georgia-Pacific plans to spend approximately $150 million rebuilding a paper machine at its Palatka, Florida, mill.

Edivro Company News · Original attributed summary. Source announcement: 2026-10-28.
Georgia-Pacific plans to spend approximately $150 million rebuilding a paper machine at its Palatka, Florida, mill. Work has begun, with completion expected in the second quarter of 2028.
Which production line is involved?
The project replaces Number Four, installed in 1980, which produces paper for Angel Soft bath tissue. Georgia-Pacific describes the investment as modernising existing tissue production and manufacturing capabilities.
Is this a newly selected mill location?
No. It is work at an established mill. The company separately refers to engineering and planning for other structured-paper-machine projects whose sites have not been announced. Those plans should not be folded into the Palatka project’s stated cost or timetable.
Source: original issuer announcement.
Questions about this story
These answers summarise the article and refer to its original reporting period.
Which production line is involved?
The project replaces Number Four, installed in 1980, which produces paper for Angel Soft bath tissue. Georgia-Pacific describes the investment as modernising existing tissue production and manufacturing capabilities.
Is this a newly selected mill location?
No. It is work at an established mill. The company separately refers to engineering and planning for other structured-paper-machine projects whose sites have not been announced. Those plans should not be folded into the Palatka project’s stated cost or timetable.
Publisher
Maya Bennett · Edivro editorial pen name