Rio Tinto tests heat-storage economics for Yarwun refinery
Rio Tinto and ARENA will each contribute A$3.6 million to a feasibility study of thermal energy storage at the Yarwun alumina refinery in Gladstone.

Edivro Company News · Original attributed summary. Source announcement: 2026-10-21.
Rio Tinto and ARENA will each contribute A$3.6 million to a feasibility study of thermal energy storage at the Yarwun alumina refinery in Gladstone. The company’s 21 October update says the study is expected to take about 12 months.
The proposed Rondo Energy system would turn electricity into heat stored in refractory bricks, then use it to generate steam. If approved, the demonstration could supply around 5% of the refinery’s steam needs.
Has the full installation been approved?
No. Later deployment support is conditional on a successful study and a decision to proceed. ARENA’s additional funding provisions should not be described as a completed operating plant. The study will assess whether the approach is technically and economically workable for part of the refinery’s heat demand.
Questions about this story
These answers summarise the article and refer to its original reporting period.
What does the article report about “Has the full installation been approved?”?
No. Later deployment support is conditional on a successful study and a decision to proceed. ARENA’s additional funding provisions should not be described as a completed operating plant. The study will assess whether the approach is technically and economically workable for part of the refinery’s heat demand.
What does this story explain about Rio Tinto tests heat-storage economics for Yarwun refinery?
Rio Tinto and ARENA will each contribute A$3.6 million to a feasibility study of thermal energy storage at the Yarwun alumina refinery in Gladstone. The company’s 21 October update says the study is expected to take about 12 months.